Save as a current project to a Project template via Teams Channel

Premium Office 365 for Workplace and Project is available under the Teams channel. I have my current project ready for future projects, and have been trying to create a template, but I could not fin...
  • Paul_Mather's avatar
    Apr 23, 2025

    Hello ujsang ,

    I think you are probably reading a guide for Project Desktop. In Project for the web / Planner Premium, you have the "Copy Plan" feature.

    Paul