Roadmaps tables missing after installing Project for the Web in a new environment

I've just installed Microsoft Project Service core and the Project Management Office Accelerator to a new environment. This appeared to be successful (apart from a known error with one of the flows i...
  • RodFromm's avatar
    Oct 31, 2023

    Rob_H68 The issue is Roadmap is only available in the default environment, which is a different url that your named instance. If you want Project for the Web and Roadmap reports in the same set of reports:,

    1. Open the .pbix file
    2. Go to Power Query
    3. Create a new Roadmap URL parameter with address
    4. For each Roadmap query, update the Source line with new Roadmap URL parameter
    5. Refresh queries
      FYI - There is already an idea submitted to allow Roadmaps in a named environment, click the link and vote Deploy Roadmap in a different environment · Community (microsoft.com)