Re: Number of assigned resources on tasks

John-project 

 

Thanks again!

If you see the pic i posted here. Im standing in the Ganth view where i have my tasks.

I was hoping i could add recources form here, and i can, but these lists i have found dont show recources

that is free(not added to any tasks.  I have 60 recources, so the list is painfully long.

I know i can go to another view and sort columns so the free recources will be in top.  I was just hoping 

i could stand in Ganth view, find tasks and from there easy get available recources so i can add.

I can see im terrible to explain:facepalm:

3 Replies

  • Vinod_Singh's avatar
    Vinod_Singh
    Copper Contributor
    This is applicable to project server, where resources are managed at organization level ( program or portfolio) . Where resources are allocated to different tasks and possibly to a different project , then project server will show you availability of all the resources and you can choose which one to assign, of course after approval and it reduces the availability of that resource automatically. In stand alone projects not all resource times dedicated to project related tasks hence best bet will be to update resources sheet and the individual availability then assign them to tasks, look for any over allocation and resolve that by resource levelling.
  • John-project's avatar
    John-project
    Silver Contributor
    Polestar2021,
    Using the Assign Resources sub-window as shown in the image you posted is the best way to assign resources while in the Gantt Chart view. Unfortunately, the list of resources is ordered by whether assigned or not. That is, assigned resources start at the beginning of the list and unassigned resources fall to the bottom of the list.

    You could also click on the selection arrow in the Resource Names field. You will see all available resources listed with a check in the box next to each that is assigned. This presentation is not sorted so it is a bit easier to see which resources are not assigned. However, checking a resource's box will automatically assign that resource at 100%.

    John
    • Vinod_Singh's avatar
      Vinod_Singh
      Copper Contributor

      John-project 

      Apply the Resource Sheet view.

      Add a number field (Number1 for example)

      Customize the field and under Calculation for task and group summary rows: select Count all

      Then apply a group by on the Group field.

       

Resources