Forum Discussion
Project planner not synchronizing tasks on other PWA projects
Good day
Recently I've noticed that our PWA projects are not considering task assignments on other projects, so we can now only level a resource only for one project. This used to happen automatically I don't know if Microsoft changed something or we changed some setting to disable the connection.
Please assist! because now we find that recourses are always over allocated
Regards
Mpafane
Hello Mpafane ,
Are you looking at the projects in MS Project? If so, do you have this option enabled when login in to the PWA account from MS Project?
Paul
Hello Mpafane ,
Are you looking at the projects in MS Project? If so, do you have this option enabled when login in to the PWA account from MS Project?
Paul
- MpafaneCopper Contributor
Paul_Mather Thank you so much that's what was wrong it now works