Project planner not synchronizing tasks on other PWA projects
Good day Recently I've noticed that our PWA projects are not considering task assignments on other projects, so we can now only level a resource only for one project. This used to happen automat...
- Oct 05, 2022
Hello Mpafane ,
Are you looking at the projects in MS Project? If so, do you have this option enabled when login in to the PWA account from MS Project?
Paul
Paul_Mather
Oct 05, 2022MVP
Hello Mpafane ,
Are you looking at the projects in MS Project? If so, do you have this option enabled when login in to the PWA account from MS Project?
Paul
Mpafane
Oct 05, 2022Copper Contributor
Paul_Mather Thank you so much that's what was wrong it now works