Project Online tasks not available in task tab

I'm trying to setup a test project and setup the following tasks in Project desktop.

 

I've successfully connected Project desktop with PWA but the issue is that the tasks in Desktop is not available online:

Desktop:

 

Project is available in Project Center:

By clicking on the Project name, you can see these tasks are synced:

 

but nothing is available in Tasks:

 

I've created myself as a resource:

 

And created timesheets (I can't edit this either):

 

I need to get this so that resources can update their own task progress, what am I doing wrong?

 

12 Replies

  • Emile --

    You have to assign yourself to one or more tasks in the project and then publish the latest changes to your project. You will also need to delete the timesheet and then recreate it. Hope this helps.
      • Dale_HowardMVP's avatar
        Dale_HowardMVP
        MVP
        Emile --

        Display the Build Team dialog. In the list of resources in the lower-right corner of the dialog, make sure that your Booking value is set to Committed. If not, specify this value, and then publish the project again. Hope this helps.