Forum Discussion
emilesteenkamp1750
Jun 14, 2023Copper Contributor
Project Online tasks not available in task tab
I'm trying to setup a test project and setup the following tasks in Project desktop. I've successfully connected Project desktop with PWA but the issue is that the tasks in Desktop is not availab...
Jun 15, 2023
Emile --
You have to assign yourself to one or more tasks in the project and then publish the latest changes to your project. You will also need to delete the timesheet and then recreate it. Hope this helps.
You have to assign yourself to one or more tasks in the project and then publish the latest changes to your project. You will also need to delete the timesheet and then recreate it. Hope this helps.
emilesteenkamp1750
Jun 15, 2023Copper Contributor
- Jun 16, 2023Emile --
Display the Build Team dialog. In the list of resources in the lower-right corner of the dialog, make sure that your Booking value is set to Committed. If not, specify this value, and then publish the project again. Hope this helps.- emilesteenkamp1750Jun 19, 2023Copper Contributor
- Jun 19, 2023Emile --
Your screenshot is of the Resource Center page. You need to click the Tasks tab to display the Tasks page in PWA. You should see your assigned tasks there. Let us know what you find.