Project Online PWA Move tasks

Anyone know if you can move tasks in the schedule in PWA/Project Online.  Have a user that isn't familiar with the desktop app and wants to move tasks up and down.  Don't remember if this ever worked.

2 Replies

  • TRobbs -- The only way to move a task using the PWA user interface is to click the row header at the far left end of the task row, and then to use Cut and Paste. In the Microsoft Project desktop application, the your user could use "drag and drop" to move the task instead. Hope this helps.
    • TRobbs's avatar
      TRobbs
      Copper Contributor
      Thanks Dale. I thought we used to be able to drag and drop. But alas, it is a browser....