Project Online PWA Move tasks
Anyone know if you can move tasks in the schedule in PWA/Project Online. Have a user that isn't familiar with the desktop app and wants to move tasks up and down. Don't remember if this ever worked...
Dec 08, 2023
TRobbs --
The only way to move a task using the PWA user interface is to click the row header at the far left end of the task row, and then to use Cut and Paste. In the Microsoft Project desktop application, the your user could use "drag and drop" to move the task instead. Hope this helps.
- TRobbsDec 08, 2023Copper ContributorThanks Dale. I thought we used to be able to drag and drop. But alas, it is a browser....