Forum Discussion

rmatsu0119's avatar
rmatsu0119
Copper Contributor
Oct 31, 2022

Project Online and On-premis difference

Hi,

I am planning to use Project and start free trial.

During the research, we found some difference between Project 2021 and Online.

Does my understanding below are collect or not?

 

1. Heatmap - Is it available only Project Online?

https://support.microsoft.com/en-us/office/evaluate-resource-capacity-in-project-online-9da06433-281c-49d3-bcf9-e1dc5d67ead4

 

2. Teams viewer - Does Project 2021 have Teams connector and can view .mpp file directly?

 

3. File CoEdit - Is Project 2021 can co-edit files by multiple users?

4 Replies

  • Hello rmatsu0119 

    1: That feature is available in Project Server On-premises (from 2016 onwards I believe - I don't use On-premises anymore, only services in Microsoft 365 so I can't confirm 100% the version) and Project Online. Not Project for the web though

    2: Project Online / Project Server / MS Project does not have a Microsoft Teams app, only Project for the web has a Microsoft Teams app

    3: Co-authoring is only supported in Project for the web, not Project Online / Project Server / MS Project

    I hope that helps

    Paul

    • rmatsu0119's avatar
      rmatsu0119
      Copper Contributor

      Dear Paul_Mather ,
      I am much appreciated for your answer.
      Currently we are comparing Project Standard 2021 and Project Plan 1.

      Based on your answer, I understand that Project Standard 2021 cannot satisfy these 3 functions.

      And Project Plan 1 have all these 3 functions.

      Thank you again for your reply. It helped me lot!

      • rmatsu0119 --

        Pardon me for bumping into this conversation. To correct you understanding, Project Plan 1 (formally known as Project for the Web) does not include a Heat Map feature. Hope this clarification helps.