Forum Discussion
Project Online and On-premis difference
Hello rmatsu0119
1: That feature is available in Project Server On-premises (from 2016 onwards I believe - I don't use On-premises anymore, only services in Microsoft 365 so I can't confirm 100% the version) and Project Online. Not Project for the web though
2: Project Online / Project Server / MS Project does not have a Microsoft Teams app, only Project for the web has a Microsoft Teams app
3: Co-authoring is only supported in Project for the web, not Project Online / Project Server / MS Project
I hope that helps
Paul
- rmatsu0119Nov 01, 2022Copper Contributor
Dear Paul_Mather ,
I am much appreciated for your answer.
Currently we are comparing Project Standard 2021 and Project Plan 1.Based on your answer, I understand that Project Standard 2021 cannot satisfy these 3 functions.
And Project Plan 1 have all these 3 functions.
Thank you again for your reply. It helped me lot!- Nov 02, 2022rmatsu0119 --
Pardon me for bumping into this conversation. To correct you understanding, Project Plan 1 (formally known as Project for the Web) does not include a Heat Map feature. Hope this clarification helps.- rmatsu0119Nov 04, 2022Copper ContributorDear Dale_HowardMVP,
Thank you for correcting my misunderstand.
To use heatmap, Project Plan 3 or 5 is required.
I will remember it.