Project for web generic resources not bookable

Hi,

on Project for Web i've created some generic resources as you can see:

Each of it with a hours calendar and bookable.

Then i've added each resource in its own plan, for example:

Pianificazione UDVC is my plan with my generic reource "Generica UDVC"

The issue is that if i try to assign a task i can only find "Member of team x" instead of "Generica UDVC" , why that name instead of the name that i wrote?

 

 

 

 

 

 

 

 

Also in some other plan i can't see any new bookable resource despite i can see the generic one from the "team" tab in Project admin portal.

Why?

 

Thanks!