Project for web generic resources not bookable
- Jan 16, 2025
Hello Saaam1165 ,
The "Generic" Resource Types are not available to assign to tasks in Project for the web - see the Note here: https://learn.microsoft.com/en-us/project-for-the-web/create-nonuser-resources-in-project-for-the-web#types-of-non-user-resources You will only be able to assign user, contact, account, or equipment resource types to project tasks in Project for the web.
Paul
Hello Saaam1165 ,
The "Generic" Resource Types are not available to assign to tasks in Project for the web - see the Note here: https://learn.microsoft.com/en-us/project-for-the-web/create-nonuser-resources-in-project-for-the-web#types-of-non-user-resources You will only be able to assign user, contact, account, or equipment resource types to project tasks in Project for the web.