Project for the Web - subtask identifier?

Hi there

Is there an easy way to identify whether a task in Project for the Web is a subtask? I'm hoping to display main project tasks only in Power BI (including a main task without subtasks). 

Any advice would be much appreciated!

  • MAC --

    The only way I can see to do this would be to use the Outline Number field. Insert that field in the Grid view and take a look at the numbering scheme. Perhaps you can use the data from this field to help you generate your Power BI report. Hope this helps.

6 Replies

    • MAC's avatar
      MAC
      Brass Contributor
      Hi Paul, unfortunately not - filtering on the summary field will only display tasks with subtasks, not standalone tasks.
      • Hello MAC ,

        Now I think I understand what you want to see, can't you use msdyn_parenttask and show only tasks where this field is null? 

        Paul

    • MAC's avatar
      MAC
      Brass Contributor
      Thanks - where can I find the WBS numbering in Project for the Web (just to clarify - I'm not using Project Online).
  • MAC --

    The only way I can see to do this would be to use the Outline Number field. Insert that field in the Grid view and take a look at the numbering scheme. Perhaps you can use the data from this field to help you generate your Power BI report. Hope this helps.