Forum Discussion

MAC's avatar
MAC
Brass Contributor
Apr 28, 2023
Solved

Project for the Web - subtask identifier?

Hi there Is there an easy way to identify whether a task in Project for the Web is a subtask? I'm hoping to display main project tasks only in Power BI (including a main task without subtasks).  An...
  • Dale_HowardMVP's avatar
    Apr 28, 2023
    MAC --

    The only way I can see to do this would be to use the Outline Number field. Insert that field in the Grid view and take a look at the numbering scheme. Perhaps you can use the data from this field to help you generate your Power BI report. Hope this helps.