Forum Discussion

LASJOHO's avatar
LASJOHO
Brass Contributor
Nov 22, 2023

Project for the web - Ongoing backup of existing project plans

Hello,

How is it possible to secure a backup of my project plans (Project for the web)?

Since several users have access to the projects and unfortunately someone has deleted tasks or changed the details in an inappropriate way without the intention.

Therefore, I would like to know if there is anyone who can help with a solution. Can it be solved with continuous backup or are there other options that I am not aware of? 🙂

 

Best regards

2 Replies

  • RodFromm's avatar
    RodFromm
    Iron Contributor

    LASJOHO Currently offers no backups for Project for the Web projects in the default environment.  If you are using a named instance, there is a restore process.  However, the process restores a backup of the entire instance to a new instance.  There are third party solutions, that supposedly will do project specific restore within an instance, but I have no experience using them.

Resources