Project for the web - Ongoing backup of existing project plans
Hello, How is it possible to secure a backup of my project plans (Project for the web)? Since several users have access to the projects and unfortunately someone has deleted tasks or changed the de...
RodFromm
Nov 22, 2023Steel Contributor
LASJOHO Currently offers no backups for Project for the Web projects in the default environment. If you are using a named instance, there is a restore process. However, the process restores a backup of the entire instance to a new instance. There are third party solutions, that supposedly will do project specific restore within an instance, but I have no experience using them.