Forum Discussion

Jason_Reece's avatar
Jason_Reece
Copper Contributor
Feb 08, 2024

Project and Planner not transferring data together

Hi,

 

I have a project plan developed in Project profession desktop which I have uploaded in to PWA. This works fine, but when I create a link to a Planner in teams, the link is created, but no information is transferred from the project into planner - it just remains blank.

 

Any thoughts?

 

Thanks.

3 Replies

  • Jason --

    The link to the Planner project is nothing more than a hyperlink. There is no data exchanged between Microsoft Project and Planner. Most people expect what you expect, but that is not how this feature works. Sorry, but hope this helps.
    • Jason_Reece's avatar
      Jason_Reece
      Copper Contributor

      Dale_HowardMVP 

       

      Hi,

       

      Thanks for the response. 

       

      That is a shame that this doesn't function as expected. It would seem almost pointless in its current implementation.

       

      Best regards,

       

      Jason.

      • Dale_HowardMVP's avatar
        Dale_HowardMVP
        MVP
        Jason --

        For whatever it is worth, I totally agree with you. What you expected from this feature is what most people expected, including me. When I discovered that the feature only created a one-way hyperlink, I was disappointed as well. It is what it is, and I doubt Microsoft will ever change this behavior. So, we live with its limitation.