Forum Discussion
Jason_Reece
Feb 08, 2024Copper Contributor
Project and Planner not transferring data together
Hi, I have a project plan developed in Project profession desktop which I have uploaded in to PWA. This works fine, but when I create a link to a Planner in teams, the link is created, but no inf...
Feb 08, 2024
Jason --
The link to the Planner project is nothing more than a hyperlink. There is no data exchanged between Microsoft Project and Planner. Most people expect what you expect, but that is not how this feature works. Sorry, but hope this helps.
The link to the Planner project is nothing more than a hyperlink. There is no data exchanged between Microsoft Project and Planner. Most people expect what you expect, but that is not how this feature works. Sorry, but hope this helps.
Jason_Reece
Feb 09, 2024Copper Contributor
Hi,
Thanks for the response.
That is a shame that this doesn't function as expected. It would seem almost pointless in its current implementation.
Best regards,
Jason.
- Feb 09, 2024Jason --
For whatever it is worth, I totally agree with you. What you expected from this feature is what most people expected, including me. When I discovered that the feature only created a one-way hyperlink, I was disappointed as well. It is what it is, and I doubt Microsoft will ever change this behavior. So, we live with its limitation.