POL task/timesheet reporting tables...

Hi team

Can someone tell me what POL report tables do I need to see the tasks and timesheet hours for a resource and their baselines on a task.
Many thanks 
James 

  • Hi James Jamesp435 ,

    Tasks details are in /_api/ProjectData/Tasks, Task time phased data is in /_api/ProjectData/TaskTimephasedDataSet, task baseline details are in /_api/ProjectData/TaskBaselines, Task baseline time phased data is in /_api/ProjectData/TaskBaselineTimephasedDataSet, timesheet time phased actual data will be in /_api/ProjectData/TimesheetLineActualDataSet. The metadata document is pretty good to view the entity details /_api/ProjectData/$metadata

    Paul

2 Replies

  • Hi James Jamesp435 ,

    Tasks details are in /_api/ProjectData/Tasks, Task time phased data is in /_api/ProjectData/TaskTimephasedDataSet, task baseline details are in /_api/ProjectData/TaskBaselines, Task baseline time phased data is in /_api/ProjectData/TaskBaselineTimephasedDataSet, timesheet time phased actual data will be in /_api/ProjectData/TimesheetLineActualDataSet. The metadata document is pretty good to view the entity details /_api/ProjectData/$metadata

    Paul