Forum Discussion

Jamesp435's avatar
Jamesp435
Brass Contributor
Apr 23, 2023
Solved

POL task/timesheet reporting tables...

Hi team Can someone tell me what POL report tables do I need to see the tasks and timesheet hours for a resource and their baselines on a task. Many thanks  James 
  • Paul_Mather's avatar
    Apr 24, 2023

    Hi James Jamesp435 ,

    Tasks details are in /_api/ProjectData/Tasks, Task time phased data is in /_api/ProjectData/TaskTimephasedDataSet, task baseline details are in /_api/ProjectData/TaskBaselines, Task baseline time phased data is in /_api/ProjectData/TaskBaselineTimephasedDataSet, timesheet time phased actual data will be in /_api/ProjectData/TimesheetLineActualDataSet. The metadata document is pretty good to view the entity details /_api/ProjectData/$metadata

    Paul