Percent Complete in Bar Chart

Some of the bars will show the dark line through the middle for %complete and some will not. I went through the same steps on the purple bars as I did the blue bars and I can't get the %complete to show up.  What am I doing wrong?

 

5 Replies

  • Robert0842's avatar
    Robert0842
    Copper Contributor

    susmatt 

     

    Hi,
    May be in the Bar Styles dialog, the purple bars are drawn under the thin bleu bar which represents the progress.

    • John-project's avatar
      John-project
      Silver Contributor
      Robert0842,
      I don't quite understand what you are saying. Are you telling me you may think the purple bar is so dark that it hides the lighter progress bar so you can't see it? If not, what are you saying?

      I asked to see a screen shot of your Bar Styles window as that could tell me a lot.
      John
      • Robert0842's avatar
        Robert0842
        Copper Contributor

        John-project 

        If the purple bar is placed under the progress bar in the Bar Styles dialog, it will mask the Progress bar.

         

         

         

         

         

        If the purple bar is placed above the Progess bar in the Bar styles dialog you will see both the purple bar and the progress bar:

         

         

         

         

         

        Hope this help (sorry for my poor English)

  • John-project's avatar
    John-project
    Silver Contributor

    susmatt 

    No way to tell from the limited information you provided. A screen shot of the Bar Styles window showing the settings for your purple bars will help.

     

    John