Newly created project is not visible in Resource Utilization view

Hi,

I created a project in PWA using New->Enterprise Project. 

Then added allocation for resources using Resource Request for this new project but when I go to Capacity Planning and select 'Resource Utilization' view, this newly created project is not visible there and the hours associated with this project showing under available hours.

Can someone please suggest how to resolve this issue

TIA!

2 Replies

  • Deepti_Gugale --

    Your mistake was using the Resource Request feature. You need to actually assign your project team members to tasks in the project before they will show up in the Resource Utilization view. Hope this helps.
    • Deepti_Gugale's avatar
      Deepti_Gugale
      Copper Contributor

      Dale_HowardMVP Thank you Dale, will try this. 

      But we are using resource request feature for existing projects and it doesnt give any issue but let me try using your suggested approach.