Newly created project is not visible in Resource Utilization view
Hi, I created a project in PWA using New->Enterprise Project. Then added allocation for resources using Resource Request for this new project but when I go to Capacity Planning and select 'Resourc...
Dec 13, 2023
Deepti_Gugale --
Your mistake was using the Resource Request feature. You need to actually assign your project team members to tasks in the project before they will show up in the Resource Utilization view. Hope this helps.
Your mistake was using the Resource Request feature. You need to actually assign your project team members to tasks in the project before they will show up in the Resource Utilization view. Hope this helps.
- Deepti_GugaleDec 13, 2023Copper Contributor
Dale_HowardMVP Thank you Dale, will try this.
But we are using resource request feature for existing projects and it doesnt give any issue but let me try using your suggested approach.