Forum Discussion
ECentric82
Dec 08, 2023Copper Contributor
Ms Projects Summary Task
Hi there. I have an issue with my task summary not being a straight line like it normally is. This doesn't impact my programme only the aesthetics of it. Can someone assist? I've looked into the information section and couldn't tell any difference in settings to the others. Thanks.
Hi Ee Yii
Try redefining the representation of summary tasks in the Gantt chart.
Go to Menu bar > Gantt Chart Format > Bar Styles > Format > Bar styles and select, if it exists, Summary, cut and paste at the end of the list.
If it does not exist, you will have to create it at the end of the list, as shown in the attached image.
Regards
Ignacio Martín
- Ignacio_MartinIron Contributor
Hi Ee Yii
Try redefining the representation of summary tasks in the Gantt chart.
Go to Menu bar > Gantt Chart Format > Bar Styles > Format > Bar styles and select, if it exists, Summary, cut and paste at the end of the list.
If it does not exist, you will have to create it at the end of the list, as shown in the attached image.
Regards
Ignacio Martín- ECentric82Copper Contributor
Ignacio_Martin Thank you for your assistance. Found the problem to be "rolled up task" bar styles instead of summary.