Ms Projects Summary Task

Hi there. I have an issue with my task summary not being a straight line like it normally is. This doesn't impact my programme only the aesthetics of it. Can someone assist? I've looked into the info...
  • Ignacio_Martin's avatar
    Dec 08, 2023

    ECentric82 

    Hi Ee Yii
    Try redefining the representation of summary tasks in the Gantt chart.
    Go to Menu bar > Gantt Chart Format > Bar Styles > Format > Bar styles and select, if it exists, Summary, cut and paste at the end of the list.
    If it does not exist, you will have to create it at the end of the list, as shown in the attached image.


    Regards
    Ignacio Martín