MS Project tasks progress approval for Project Manager does not work
Hi all!
I am setting up Project Onilne in my organization, unfortunatelly we don't have experienced professional in Project Server settings, and it looks quite tricky for me to understand all of them.
I also tried searcing the Internet, but didnt sucseed, it looks like functionality I'm asking below have to work by default, but it's not.
Here is the problem itself: user set to be project manager doesn't see time reports, which are sent by project team members for approval.
What I got in place:
- project exists on server
- project team can see it and work with it: team can enter hours at the area "my tasks" accessed from leftside quick launch menu, team members also successfully send hours for approval
- User, who should approve progress has the following settings (just checked right now):
** he is included in "Timesheet managers" (I have read somewhere that this appointment applies from the next schedule created and i created schedule after appointment done)
** he is included in "Project Managers" group, "Project Managers" group has included categories "My Tasks" and "My Projects"
** These categories "My Tasks" and "My Projects" have permissions set with default template sets of permissions for "Team member" and "Project Manager" correspondingly.
** global permissions for group "Project Managers" are set with "Project manager" template
"Timsheet settings and defaults" section option "Task Status Manager Approval" is set to "Enabled" and "Require line approval before timesheet approval" turned on.
Me, having admin rights can see all tasks & their hours submitted for approval.
Could you please advise if I missed somthing in settings of server or permissions for groups to give Project Manager ability to approve task hours submitted by team?
- Илья, необходимо создать задачу в WEB под другим пользователем и опубликовать проект.
После публикации в выпадающем списке кроме Вас появится и этот человек.
Тот кто будет утверждать задачи в этом проекте должен хотя-бы один раз создать и опубликовать хоть одну задачу, далее его можно будет выбрать утверждающим в других:)
7 Replies
- Vasily_ZaytsevIron ContributorHello, Ilya. Each project task has field Status Manager. Only Status Manager can approve the task.
If you create a task, you are a Status Manager of this task if you don't change his field.
BR, Vasily- IlyaAdadurovTin ContributorI suppose this should help, Asked my admins to change Office interface to English (it is in Russian for now).
While it is not English I cand find "Status Manager" column in Project Desktop App, in Russian it should be "менеджер состояний", but there is no such column name when I try to add new column.- Vasily_ZaytsevIron ContributorIn Russian it is "Управляющий назначением"