Forum Discussion
IlyaAdadurov
Jul 07, 2022Tin Contributor
MS Project tasks progress approval for Project Manager does not work
Hi all! I am setting up Project Onilne in my organization, unfortunatelly we don't have experienced professional in Project Server settings, and it looks quite tricky for me to understand all of the...
- Jul 07, 2022Илья, необходимо создать задачу в WEB под другим пользователем и опубликовать проект.
После публикации в выпадающем списке кроме Вас появится и этот человек.
Тот кто будет утверждать задачи в этом проекте должен хотя-бы один раз создать и опубликовать хоть одну задачу, далее его можно будет выбрать утверждающим в других:)
Vasily_Zaytsev
Jul 07, 2022Iron Contributor
Hello, Ilya. Each project task has field Status Manager. Only Status Manager can approve the task.
If you create a task, you are a Status Manager of this task if you don't change his field.
BR, Vasily
If you create a task, you are a Status Manager of this task if you don't change his field.
BR, Vasily
IlyaAdadurov
Jul 07, 2022Tin Contributor
I suppose this should help, Asked my admins to change Office interface to English (it is in Russian for now).
While it is not English I cand find "Status Manager" column in Project Desktop App, in Russian it should be "менеджер состояний", but there is no such column name when I try to add new column.
While it is not English I cand find "Status Manager" column in Project Desktop App, in Russian it should be "менеджер состояний", but there is no such column name when I try to add new column.
- Vasily_ZaytsevJul 07, 2022Iron ContributorIn Russian it is "Управляющий назначением"
- IlyaAdadurovJul 07, 2022Tin ContributorOne more step forward, thanks a lot!
Got it, but there is only me in the drop-down list and I can't put another name in the cell.
Is there a place where the list of "Status Managers" is created? Is it inside particular Project or is it set on Server?- Jul 07, 2022Ilya --
The project manager of the project in question must open and check out the project. Then he must insert the Status Manager column, and select his own name for every detailed task in the project. Then the project manager must save and publish the project. There is no way for YOU to set the Status Manager to someone else. It must be done by the current project manager. Hope this helps.