Forum Discussion

Roudy_El_Hader's avatar
Roudy_El_Hader
Copper Contributor
Apr 12, 2021

MS Project, ProjectCostvariance calcualtion, is calculated based on which Project baseline ?

Hello,

Is there a field in the MS Project tables (reporting DB), that identify the ProjectCostVariance, is calculated based on which baseline. Supposedly, a project has multi baselines created.

I need to know if this information is stored in any field ?

 

if this information is stored on Task level, can do the work too.

 

Thanks in advance.

1 Reply

  • Roudy_El_Hader 

    I believe that you won't have this setting in the reporting DB since this is a desktop MS Project setting. This setting is used only in MS Project (and not in the DBs) to calculate EVM data in MS Project.

    Note that EVM calculation uses by default the baseline 0.