Forum Discussion
Roudy_El_Hader
Apr 12, 2021Copper Contributor
MS Project, ProjectCostvariance calcualtion, is calculated based on which Project baseline ?
Hello, Is there a field in the MS Project tables (reporting DB), that identify the ProjectCostVariance, is calculated based on which baseline. Supposedly, a project has multi baselines created. I n...
Guillaume Rouyre
Apr 28, 2021Brass Contributor
I believe that you won't have this setting in the reporting DB since this is a desktop MS Project setting. This setting is used only in MS Project (and not in the DBs) to calculate EVM data in MS Project.
Note that EVM calculation uses by default the baseline 0.