Forum Discussion

sirsleep29's avatar
sirsleep29
Brass Contributor
Jun 06, 2023

MS Project Help Needed

All,

 

I have a task that needs to start exactly 6 months after another task. Would the best way to go about building that in the schedule be to make the earlier task a start to start predecessor and add on 6 months of lag time? Sorry if it is a "newbie" question but haven't used MS Project in 20 years and trying to teach myself and learn. I appreciate the help.

 

Thank You

  • John-project's avatar
    John-project
    Silver Contributor
    sirsleep29,
    Yes that would be the best way, but. . . are you looking for a delay of 6 working months or 6 calendar months? Entering Xss+6mon as the task dependency will give you 6 working months which are by default 20 days per month. However, if what you really want is 6 calendar months, then use: Xss+6emon.

    Hope this helps.
    John

Resources