MS Project Help Needed
All, I have a task that needs to start exactly 6 months after another task. Would the best way to go about building that in the schedule be to make the earlier task a start to start predecessor a...
John-project
Jun 06, 2023Silver Contributor
sirsleep29,
Yes that would be the best way, but. . . are you looking for a delay of 6 working months or 6 calendar months? Entering Xss+6mon as the task dependency will give you 6 working months which are by default 20 days per month. However, if what you really want is 6 calendar months, then use: Xss+6emon.
Hope this helps.
John
Yes that would be the best way, but. . . are you looking for a delay of 6 working months or 6 calendar months? Entering Xss+6mon as the task dependency will give you 6 working months which are by default 20 days per month. However, if what you really want is 6 calendar months, then use: Xss+6emon.
Hope this helps.
John