MS Project % Complete Calculations Derived from Actual Work (Costs) Completed and EAC?

Does Microsoft Project have an option (especially one that can be defaulted to) to calculate % complete based on actuals divided by EAC for a given task (which could then also be rolled up to higher levels of indenture) instead of having % complete an "entered" field?

  • Mike_Murphy365,
    Simple answer, no. That said, a custom field can be created with a formula to calculate actuals (need to define exactly what that means to you) divided by EAC. If you want that new calculated value to actually appear in the % Complete field, that can also be done with some VBA.

    Hope this helps.
    John

3 Replies

  • John-project's avatar
    John-project
    Silver Contributor
    Mike_Murphy365,
    Simple answer, no. That said, a custom field can be created with a formula to calculate actuals (need to define exactly what that means to you) divided by EAC. If you want that new calculated value to actually appear in the % Complete field, that can also be done with some VBA.

    Hope this helps.
    John
    • Mike_Murphy365's avatar
      Mike_Murphy365
      Copper Contributor

      John-project Excellent, thank you!  It would ne nice if this was something hardwired in as an option since I have seen a trend in this "angle-of-attack", especially when objective completion / % criteria are a challenge.  Thanks again.

      • John-project's avatar
        John-project
        Silver Contributor
        Mike,
        You're welcome and thanks for the feedback. I suggest you submit a request through Project's Feedback portal found at the bottom of the Project splash screen.
        John