MS Project % Complete Calculations Derived from Actual Work (Costs) Completed and EAC?

Does Microsoft Project have an option (especially one that can be defaulted to) to calculate % complete based on actuals divided by EAC for a given task (which could then also be rolled up to higher ...
  • John-project's avatar
    Mar 23, 2022
    Mike_Murphy365,
    Simple answer, no. That said, a custom field can be created with a formula to calculate actuals (need to define exactly what that means to you) divided by EAC. If you want that new calculated value to actually appear in the % Complete field, that can also be done with some VBA.

    Hope this helps.
    John