Forum Discussion

gary_wiley's avatar
gary_wiley
Copper Contributor
Oct 29, 2021

Lead time not reflected in "Early Start"

I have built a schedule with predecessor links. I have added a FS-10 day lead time, but it is not reflected in the Early Start column. The Early Start still shows the day after the predecessor finish. Any advice?

 

Edit... I also changed Early Start to Start, and still no success.

 

Thanks,

  • John-project's avatar
    John-project
    Silver Contributor

    gary_wiley 

    Does the Gantt Bar reflect the 10 day lead? Does the task have any other predecessors that may be holding it from starting earlier? And I assume the task has no constraints, right?

     

    Is calculation set to automatic? Are all tasks auto-scheduled? Is any leveling applied?

     

    A screen shot could be helpful.

    John

Resources