Forum Discussion

SaraFennah's avatar
Sep 14, 2016
Solved

lag time defaulting to edays in Project 2016

Has anyone else seen lag defaulting to edays in Project 2016?  It only happends when using the task information dialog to enter lag but then has to be edited in the cell/edit bar back to days.  Most Frustrating!  I've sent a frown.

  • Hi Sara - this is a known issue.  See:

     

    https://social.technet.microsoft.com/Forums/projectserver/en-US/f894a46c-7cbb-4a10-9d22-36786a137942/changing-lag-between-linked-tasks-changes-automatically-to-elapsed-time-in-project-2016-since?forum=projectprofessional2010general

     

    for some recommended work arounds.

3 Replies

  • Julie Sheets's avatar
    Julie Sheets
    Copper Contributor

    Hi Sara - this is a known issue.  See:

     

    https://social.technet.microsoft.com/Forums/projectserver/en-US/f894a46c-7cbb-4a10-9d22-36786a137942/changing-lag-between-linked-tasks-changes-automatically-to-elapsed-time-in-project-2016-since?forum=projectprofessional2010general

     

    for some recommended work arounds.

    • SaraFennah's avatar
      SaraFennah
      MVP
      Thanks Julie - good to know its not just me. The best workaround I've found is typing directly into predecessors column.
  • Adrian Adam's avatar
    Adrian Adam
    Copper Contributor

    Hi Sara

     

    just tested and for me it keeps correctly "elapsed days" or "days" depending of what I typed into Lag-field. Tested with version: 16.0.4432.1000 32 bit...maybe it came with a later update.

    Adrian

Resources