Forum Discussion

SaraFennah's avatar
Sep 14, 2016
Solved

lag time defaulting to edays in Project 2016

Has anyone else seen lag defaulting to edays in Project 2016?  It only happends when using the task information dialog to enter lag but then has to be edited in the cell/edit bar back to days.  Most ...
  • Julie Sheets's avatar
    Sep 17, 2016

    Hi Sara - this is a known issue.  See:

     

    https://social.technet.microsoft.com/Forums/projectserver/en-US/f894a46c-7cbb-4a10-9d22-36786a137942/changing-lag-between-linked-tasks-changes-automatically-to-elapsed-time-in-project-2016-since?forum=projectprofessional2010general

     

    for some recommended work arounds.