Forum Discussion

BKirby88's avatar
BKirby88
Copper Contributor
Mar 30, 2023

Lag settings

I have two calendars set up one with a standard week & another weekends only. I want to add a lag for a task which is a weekend activity with the standard week calendar and not the weekend only calendar. Is this possible? 

  • Bkirby88 --

    If you want the task to occur on a weekend, you need to apply the weekend work calendar to the task. Does that help? If not, please follow up with additional questions. Thanks!
    • BKirby88's avatar
      BKirby88
      Copper Contributor
      Hi,

      Not quite.
      For example:
      Task 1 - Issue purchase order to supplier ( Weekday calendar )
      Task 2 - Complete work ( Weekend working ). I want to add a 60day Leadtime from the purchase order until the start of task 2 but it used the weekend working calendar, but the 60day lead time is during the normal working week.
      • PlannersPlace's avatar
        PlannersPlace
        Brass Contributor

        BKirby88

         

        The lag between Tasks 1 & 2 should be 24 days.

         

         

        60 days in Standard calendar equals 12 weeks. 12 weeks in Weekend calendar is 12 x 2 days = 24 days.

         

        =jerome

        @PlannersPlace 

Resources