Integration MS Project and Power BI

Greetings,

 

Can someone clarify the above-mentioned subject: What is the current situation?

 

Thx

  • Hello Javanshir ,

    Is this for MS Project Desktop / Project Professional and Power BI? If so, that is not possible directly. You could look at exporting the Project data from Project Desktop into Excel and using the Excel file as a data source in Power BI.

    Paul