Forum Discussion
Charles130123
Jan 13, 2023Copper Contributor
Import Wizard to update fields in existing project
I am using the Import Wizard to update two fields in my existing project using the Unique ID as a key. The two fields are both Textxx fields. When I import, I get
for every task and it either deletes all the start/finish/duration details (Yes) or just the duration and effort fields (no). I don't want MSP to touch these fields.
What can I do?
Thanks
Charles
14 Replies
Sort By
- John-projectSilver ContributorCharles130123,
First of all, what version of Project are you using?
Are you attempting to Append or Merge the data?
What are the two fields you are tying to update?
Also, a screen shot of your import map would be useful.
John- Charles130123Copper Contributor
Thanks for replying. Answers below. Charles
Version:
Import Wizard:
MS_Planner_ID is Text10
MS_Planner_Completed_Off is Text16
Grateful any help on this. An example of before and after is:
Before:
After (replying No to above dialog box)
- Charles130123Copper ContributorMight be worth adding that the required fields are updated - I just don't want this side effect (obviously!). I am sure this has worked before (I have used it for two years) - and also not worked before. So I don't know what is different? Maybe a silent MS Project version upgrade?
Charles
Any suggestions gratefully received.