Import Wizard to update fields in existing project
I am using the Import Wizard to update two fields in my existing project using the Unique ID as a key. The two fields are both Textxx fields. When I import, I get for every task and it either...
Charles130123
Jan 14, 2023Copper Contributor
Thanks for replying. Answers below. Charles
Version:
Import Wizard:
MS_Planner_ID is Text10
MS_Planner_Completed_Off is Text16
Grateful any help on this. An example of before and after is:
Before:
After (replying No to above dialog box)
Charles130123
Jan 14, 2023Copper Contributor
Might be worth adding that the required fields are updated - I just don't want this side effect (obviously!). I am sure this has worked before (I have used it for two years) - and also not worked before. So I don't know what is different? Maybe a silent MS Project version upgrade?
Charles
Any suggestions gratefully received.
Charles
Any suggestions gratefully received.