How to trigger a flow when a specific custom filed data is added or changed in project online?

ex: In Power automate the flow will run based on this trigger ,when  a project is published.  I had a custom filed Project Level Entity, custom filed name is Quantity that is  tagged in a project detail page.

Whenever the end user enter the data in Quantity custom filed ,flow has to trigger based on this filed.

Ex: Quantity :10 (flow has to run)

     if the Quantity value gets changed

    Quantity : 20 (flow has to run)

I am creating a project snapshot using Sp list & power automate. I just want to track that custom filed data in project online.

  • Hello Anil_kumar ,

    There isn't a Power Automate flow trigger for a field change for Project Online, all you can do is fire the flow when the project is published. If you are tracking the data in an SP list, you could compare the data in the project and the latest record in the SP list to see if the field value changed or not.

    Paul

7 Replies

  • Hello Anil_kumar ,

    There isn't a Power Automate flow trigger for a field change for Project Online, all you can do is fire the flow when the project is published. If you are tracking the data in an SP list, you could compare the data in the project and the latest record in the SP list to see if the field value changed or not.

    Paul

    • Anil_kumar's avatar
      Anil_kumar
      Brass Contributor

      Thanks for the response & for the suggestions Paul_Mather ,

      In power automate, I am facing some logical issues for this flow. The flow shows successfully run but the condition is not executing Paul. Please suggest the steps for this flow, That would be a great help 

      • Paul_Mather's avatar
        Paul_Mather
        MVP

        Hi Anil_kumar ,

        This will be quite tricky to debug via the forum. How come you are doing to calls to SharePoint then doing two foreach loops - one for each data set returned from the SP actions? If you are comparing Project A from PWA and Project A from the SP list, I would expect just one SP action to get the latest record from the SP list for Project A so you can compare that?

        Paul