How to trigger a flow when a specific custom filed data is added or changed in project online?

ex: In Power automate the flow will run based on this trigger ,when  a project is published.  I had a custom filed Project Level Entity, custom filed name is Quantity that is  tagged in a project det...
  • Paul_Mather's avatar
    Mar 09, 2022

    Hello Anil_kumar ,

    There isn't a Power Automate flow trigger for a field change for Project Online, all you can do is fire the flow when the project is published. If you are tracking the data in an SP list, you could compare the data in the project and the latest record in the SP list to see if the field value changed or not.

    Paul