How to delete/remove Team Member from a Project in Project for the Web?
Hello,
We're using the Project for the Web accelerator Power App.
A bookable resource can be added directly to a Project via the Project's Resources tab or if they're assigned to a Task. When they are added to a Project, they will show up under the Resources tab as a "Team Member" (in the "Project Team Members"/"msdyn_projectteam" table).
However, when I try to Delete them from the Project's Resource tab, I get the following error:
If I delete all of their Tasks or unassign them from all Tasks, they still show as a Team Member under the Resources table and still cannot be deleted.
How can we delete a Team Member from a Project within P4W?
Thanks,
Adil
11 Replies
- Adil365 --
I believe the only way to remove a team member from the project group would be by someone who has permissions to do so with Office 365 Groups. It is not possible to remove team members in Project for the Web. Hope this helps.- Neil_KellyCopper Contributor
Dale_HowardMVP ah interesting. I assumed since adding a team member adds to the office group. It would do the reverse automatically. I'll try removing from the group first and see whether it's possible then. Thanks for the suggestion. I'll report back here. To confirm either way.
- DannyWiederCopper ContributorHi Neil - did you manage to get anywhere with this? We have the same issue.
- Neil_KellyCopper ContributorWe have this issue as well and would love to know the answer to it.