Forum Discussion

MattColl666's avatar
MattColl666
Copper Contributor
Jul 20, 2023

How can you Display Summary Task % Complete In a Project Centre View

Hi, We use PWA and I'm trying to create a view in Project Center that displays amongst other stuff the % complete for each Summary Task. I can get it to display the % complete for an individual task but not the summary tasks. 

 

Is there a way to bring in the % Complete for each summary?

 

All our plans always contain the following Phases (Summaries)

 

For reference, this is how I currently bring % Complete for a single task into the Project Center View:

 

Many thanks in advance

Matt Collins

1 Reply

  • MattColl666's avatar
    MattColl666
    Copper Contributor

    MattColl666 

    I thought I would try and add some further info. Below is a snapshot of the Project Center View I am trying to create. Production % Work Complete comes from a single task in the plan and rolls up to the project level with no problem but Design % Work Complete is made of multiple lines so the Design Phase summary % Complete will not pull through to the project level for reporting purposes. Any help as to why and how I could overcome this would be much appreciated:

    Cheers

     

    Matt Collins

     

Resources