Forum Discussion
MattColl666
Jul 20, 2023Copper Contributor
How can you Display Summary Task % Complete In a Project Centre View
Hi, We use PWA and I'm trying to create a view in Project Center that displays amongst other stuff the % complete for each Summary Task. I can get it to display the % complete for an individual task ...
MattColl666
Sep 05, 2023Copper Contributor
I thought I would try and add some further info. Below is a snapshot of the Project Center View I am trying to create. Production % Work Complete comes from a single task in the plan and rolls up to the project level with no problem but Design % Work Complete is made of multiple lines so the Design Phase summary % Complete will not pull through to the project level for reporting purposes. Any help as to why and how I could overcome this would be much appreciated:
Cheers
Matt Collins