Hide time between tasks

Hi all,

 

I just upgraded from project 2003 to 365.

 

There is something I am hoping the latest version can do, that I could never figure out if I could do it in 2003.

 

If I have two tasks, say 6 months apart.  Task 1 ends in January and Task 2 starts in say July.  I would like to not show the time between the tasks, or show an abbreviated portion of the time between the tasks in the printed view.  I would like to do this without changing the timescale.

 

Kind of like in a spreadsheet where you would hide columns.

 

 

Does that make sense to anyone?  Is it possible?

 

Thanks,

 

Arthur

  • Arthur,
    Yes, it makes perfect sense and other users have made a similar request. Unfortunately Project still doesn't have any way to "block out" portions of the timeline.

     

    I suggest you submit a request via the Feedback channel in Project (File > Feedback) - "I have a suggestion".

    John

2 Replies

  • John-project's avatar
    John-project
    Silver Contributor

    Arthur,
    Yes, it makes perfect sense and other users have made a similar request. Unfortunately Project still doesn't have any way to "block out" portions of the timeline.

     

    I suggest you submit a request via the Feedback channel in Project (File > Feedback) - "I have a suggestion".

    John