Hide time between tasks

Hi all,   I just upgraded from project 2003 to 365.   There is something I am hoping the latest version can do, that I could never figure out if I could do it in 2003.   If I have two tasks, sa...
  • John-project's avatar
    Nov 01, 2023

    Arthur,
    Yes, it makes perfect sense and other users have made a similar request. Unfortunately Project still doesn't have any way to "block out" portions of the timeline.

     

    I suggest you submit a request via the Feedback channel in Project (File > Feedback) - "I have a suggestion".

    John