Forum Discussion

gautiercoadou's avatar
gautiercoadou
Copper Contributor
Mar 01, 2023

Getting values of "start" and "end" for a summary task

Hello,

 

I have trouble getting the value (the date) printed in "start" or "end" column for summary tasks. 

For some of the summary tasks i get "NC" or the starting date of the project.

 

Looking forward to your help

  • John-project's avatar
    John-project
    Mar 01, 2023
    gautiercoadou,
    Thanks for the screen shot. It allowed me to understand and determine what is wrong. I think the issue is a simple matter of you forgetting to check the box to use the formula for "calculations for task and group summary rows" for your custom date field "Copie ? fin".

    John
  • John-project's avatar
    John-project
    Silver Contributor
    Gautiercoadou,
    First of all, what version of Project are you using (i.e. Project desktop, Project plan 1, 3 or 5, etc.)?

    When you say "printed" do you mean what you see on your screen or what you see when you print?

    Are your tasks auto-scheduled or manually scheduled?

    A screen shot would be extremely helpful.

    John
    • gautiercoadou's avatar
      gautiercoadou
      Copper Contributor

      First of all thanks for you answer

       

      I use Project desktop version 2301 build 16026.20200

       

      Below you can see a printscreen

       

      A littrle bit of explanations here

      "Début" means "start",

      "Fin" means  "End"

       

      "Copie ? début" is a date-type custom fiels with a formula [Copie ? début] = [début]

      "Copie ? fin is a date-type custom fiels with a formula [Copie ? fin] = [fin]

       

      I also tried with start-type custom field but it still didn't work

       

      As you can see, fo my summary task Marché GOF

      the value of "Copie ? début " should be 27-02-23, and i get "03-02-20"

      the value of "Copie ? début " should be 06-07-23, and i get "NC"

       

      Regards

       

      • Dale_HowardMVP's avatar
        Dale_HowardMVP
        MVP

        gautiercoadou -

        You missed one step in creating the formula in each of these two custom fields.  In the Custom Fields dialog, select one of the fields containing the formula and then select the Use Formula option in the middle of the dialog, such as shown below.  Do the same for the other formula as well.  Your formula should now work correctly in both of the custom fields.  Hope this helps.

         

         

  • gautiercoadou --

    Are you using Manually Scheduled tasks in your project? If so, change them to Auto Scheduled and let us know what happens. Thanks!

Resources