Getting values of "start" and "end" for a summary task

Hello,   I have trouble getting the value (the date) printed in "start" or "end" column for summary tasks.  For some of the summary tasks i get "NC" or the starting date of the project.   Lookin...
  • John-project's avatar
    John-project
    Mar 01, 2023
    gautiercoadou,
    Thanks for the screen shot. It allowed me to understand and determine what is wrong. I think the issue is a simple matter of you forgetting to check the box to use the formula for "calculations for task and group summary rows" for your custom date field "Copie ? fin".

    John